DUARTE, Los Angeles County — October 25, 2026. Construction continues on the Donald and Bernice Watson Recreation Trail, a roughly 1.6-mile walking and cycling corridor between Buena Vista Street and Royal Oaks Park. Duarte’s official project page says that during October 2026 the contractor expects to install park furniture, work on landscaping and irrigation, and begin the lighting portion of the improvements.

What work is planned for October?

According to the city’s latest project update, the planned tasks include grading areas between the asphalt and dirt paths, installing benches and dog-bag dispensers, irrigation grading and landscaping, and electrical work on security lighting. The project is designed to improve safety and accessibility along the trail, while adding wayfinding signs and rest areas.

Has the paving been completed?

The city says the contractor completed paving in September 2026, but other construction and cleanup tasks continue. It reported wind sculptures installed along the trail and landscaping still to come. Finishing pavement is not the same as completing the entire project. The city’s stated overall target remains winter 2026, subject to construction conditions.

What about trail detours and closures?

Duarte warns that sections of accessible pathways may be temporarily interrupted during construction. The city asks visitors to follow signs, orange fencing and cones that identify uneven surfaces and temporary work conditions. FS Contractors, Inc. says it will try to maintain safe alternative routes when possible, but a continuous accessible detour is not guaranteed at every location or hour. Cyclists and people with mobility needs should review the latest notice before planning their route.

What will happen to the trees?

The city says an arborist reviewed 40 Engelmann oak trees planted near the trail about two decades ago, finding that some had been planted improperly and had become stressed. Project plans call for removing and replacing 25 affected trees, with continuing arborist monitoring. The city identifies the trees as an important native landscape feature of the San Gabriel Valley foothills. The project updates should be consulted for any change to the removal or replacement plan.

Who is paying for the improvements?

The city lists a combination of federal Community Project Funding awarded in 2023 and Measure M funds. The project’s contractor is FS Contractors, Inc., with separate engineering, landscape-architecture and lighting partners. These funding sources do not establish a final construction cost unless verified in a project budget or contract amendment.

Follow the City of Duarte’s updated project tracker, rather than an outdated map, for current conditions. Visit Duarte News for local community information.

Primary sources: Duarte construction announcement and municipal trail project updates, checked October 25, 2026. Schedules are subject to change.

Help Duarte News grow Help strengthen reporting on Duarte: community voices, important decisions and local life.
Support Duarte News

Choose how to support Duarte News:

Credit / Debit Card via Stripe

Choose your contribution amount on the secure California58 Stripe checkout. One-time support for independent local journalism.

Continue with PayPal Continue with Zelle

Zelle payments go to Vitaly Ataev Troshin. Please verify the recipient in your bank before sending. Availability depends on your bank.

Optional reader support. When possible, add “Duarte News” to the payment note. Contributions are not advertised as tax-deductible. Support does not influence editorial decisions.

Duarte News — Your Community Newspaper

Have a correction, news tip, local announcement, or story to submit? Contact our editorial team. All submissions are reviewed before publication.

Contact the Duarte News newsroom →

More from Duarte News

Visit Duarte News →

COMMUNITY

Comments

Join the California58 conversation. You must be signed in to comment.